How It Works

Sarawak NEM Guide

A practical guide to Sarawak Energy's grid connection and crediting arrangement: who can apply, how capacity is assessed and what happens before a system is connected.

NEM: connection and bill crediting

Sarawak Energy credits the electricity measured under the approved NEM arrangement according to the applicable contract and billing rules. Consumption and PV export are measured separately. Confirm the applicable crediting and settlement terms; this guide does not assume a one-for-one tariff or promise a cash payout.

The residential subsidy is a separate financial incentive with its own qualifying contract dates, capacity bands and quota. Its published end date does not end NEM itself.

Read the Solar Subsidy Guide

Sarawak Energy: NEM guidance and subsidy FAQs

NEM Eligibility Requirements

  • NEM is open across tariff categories to applicants connected to Sarawak Energy's grid. The residential subsidy has its own, narrower eligibility rules.
  • The published guidance excludes applicants with more than two months of outstanding bills or a pending meter-tampering case.
  • General eligibility excludes connected energy storage. SEB's FAQ describes possible battery exceptions with appropriate protection; see the battery answer below and obtain project-specific confirmation.
Read the NEM questions

Sarawak Energy: NEM guidance and subsidy FAQs

Capacity, sizing and metering details

Published standard limits are 10 kWac for single-phase and 30 kWac for three-phase connections. Systems above 30 kWac require a power system study; above 50 kWac requires consultation and a special arrangement with Sarawak Energy's Single Buyer. Local network limits and approval conditions also apply.

Sarawak Energy's published sizing rule limits generated energy to no more than 75% of average consumption over the previous 3 months. This is an energy-generation requirement, not a rule to take 75% of a panel's DC rating. Transformer and connection-point limits can further restrict capacity.

Sarawak Energy: NEM guidance and subsidy FAQs

SEB NEM Application Process

These stages show the general responsibilities of the customer, appointed contractor and Sarawak Energy. They are a guide to the dependencies, not an unconditional installation or approval timetable.

  1. Customer

    Appoint a registered contractor

    Choose an appropriate registered NEM contractor and confirm the required EIU-competent personnel for the work.

  2. Appointed contractor / competent personnel

    Prepare and submit the application

    The appointed contractor prepares the current forms, drawings, supporting documents and consumption information, then submits them on your behalf.

  3. Sarawak Energy

    Application review

    Sarawak Energy reviews the application, network conditions and any required study, then issues the applicable acceptance or approval.

  4. Appointed contractor / competent personnel

    Installation to the required design

    Coordinate installation with the approved technical requirements. Starting work early may leave the customer responsible for the cost of required changes.

Documents, forms and professional competencies

Typical requirements include current NEM and PV meter forms, contractor appointment, premises/layout information, owner consent for rented premises, recent bills, inverter specifications, endorsed electrical drawings and the relevant competency certificates. Use Sarawak Energy's current list: the replacement NEM application form became mandatory in 2026.

Sarawak Energy's competency notice distinguishes PV design, installation, drawing endorsement and testing roles. Design can use the specified EIU-certified or EIU-authorised GCPV designer; testing and commissioning endorsement requires an EIU-certified GCPV designer. Confirm the appropriate installer and AC endorsement competencies for the system. This guide does not certify any contractor.

Sarawak Energy: EIU competency update (7 May 2026)

Sarawak Energy: new NEM application form notice

Find contractors in Sarawak Energy's official directory

Sarawak Energy: NEM guidance and subsidy FAQs

Testing, Commissioning and Meter Installation

  1. Testing and reports

    Required competent personnel perform testing and commissioning checks and submit the reports required for the NEM contract and PV meter stage.

  2. Contract and metering payment

    Complete the NEM contract and applicable PV metering payment requirements when instructed by Sarawak Energy.

  3. PV Meter and Final Connection

    Sarawak Energy's authorised personnel carry out the applicable meter and live-connection work. Confirm the final connection and commissioning steps with SEB; submitting an application is not permission to energise the system.

Testing reports are required for the contract stage. Sarawak Energy also requires the NEM contract before PV meter installation and final system commissioning. Confirm the detailed testing, energisation and metering sequence with the appointed contractor and Sarawak Energy; the stages can involve intermediate requirements.

A separate PV meter measures export. Sarawak Energy's current guidance calls for a conventional consumption meter to be replaced with a smart meter. Sarawak Energy determines the final arrangement and carries out the applicable meter and live-connection work.

Published PV smart-meter unit prices
Meter typePublished unit price
Single-phase smart meterRM500
Three-phase smart meterRM1,000

These are published unit prices, not a Solar Halo quotation. Other connection charges are also borne by the customer. Confirm the current charges and scope with Sarawak Energy.

Sarawak Energy: NEM guidance and subsidy FAQs

NEM Questions That Need a Closer Look

These answers explain important qualifications. Sarawak Energy and your appointed contractor should confirm the requirements for your property.

How long does an NEM application take?

SEB's FAQ publishes 14 days for applications without a system study, and 30 days for a first study submission with 14 days for subsequent submissions. These are published processing periods, not an installation schedule or a Solar Halo promise. Confirm the applicable timing with SEB.

Can batteries be connected under NEM?

SEB's general eligibility guidance excludes connected storage. Its FAQ says a battery connection may be considered with suitable anti-islanding measures and fault protection. This is not blanket permission: obtain project-specific confirmation from SEB before including batteries.

What if an application is not approved?

A proposal or submission is not approval. Ask SEB and the appointed contractor about the reasons, revisions or studies needed before proceeding. SEB warns that work started early can leave required modification costs with the customer; do not assume approval, reimbursement or subsidy.

FAQ

Sarawak Energy: NEM guidance and subsidy FAQs

Your next step

Start your solar conversation.

Tell us where you are and what you have in mind.

Get a Quote